A small water utility has a treatment plant, an office, and a remote tank or booster site. Its network grew a device at a time. Office computers, control-system equipment, cameras, and vendor access now share more than anyone intended.
The staff does not need a more impressive diagram. It needs to know what can talk to what, what happens when a link fails, and how to get help without opening the entire plant to the internet.
Here is how I would map the dependencies, stage the changes, and establish whether the finished network does what the operators need.

Start with the process, not the VLAN numbers
Before changing a boundary, sit down with the operators and the control-system owner. Identify the HMI and historian, the controllers and remote telemetry, the alarm paths, and the people who maintain them. Ask what must continue locally if the office, internet, or remote link disappears.
A controller’s safety and process behavior is not something a network engineer should infer from a packet capture. The utility and its controls specialists must establish the operating limits, change windows, and recovery steps.
Then record the flows the process actually needs. “SCADA” is too broad to be a firewall rule, just as “maintenance” is too broad to be a purchase order.
| Example flow to validate | Boundary question | Acceptance evidence |
|---|---|---|
| Approved HMI → named controller | Which protocol, direction, and timing does the controls owner require? | Operator verifies normal indications and authorized functions before and after the change. |
| Office user → operational reports | Can reports be provided through an approved intermediary instead of direct controller access? | Required reports work; unrelated operational destinations remain inaccessible. |
| Vendor → assigned maintenance endpoint | Which named person, approved window, and target? | The task works; other targets and access after closure are denied. |
| Remote-site infrastructure → monitoring | Which telemetry is supported and safe to collect? | Link and power alarms identify the affected site without implying every hidden device has failed. |
These are discussion prompts, not deployable firewall rules. Actual addresses, ports, application dependencies, and process constraints belong in the utility’s private documentation.
Make the boundaries readable
I would separate business IT, operational systems, infrastructure management, cameras, and guest access according to their purpose and risk. An engineering workstation or historian belongs where its function and trust relationships warrant, not automatically in an office zone because it runs Windows.
Inter-zone access should cross a deliberate, monitored policy boundary. Permit the approved flows and deny the rest. Merely assigning different VLAN numbers does not prevent a router from allowing everything between them.
This direction follows EPA’s water-sector segmentation guidance: separate IT from OT, explicitly authorize necessary connections, and use monitored intermediaries at the boundary. NIST’s OT security guidance adds the essential context: availability, safety, and operational constraints shape how controls are applied.
At a remote tank, carry only the services the site needs. A camera may justify a security zone; an HMI may justify an operational workstation zone. The office guest network does not need a scenic trip to the tank.
Replace permanent openings with an access procedure
Vendor access needs more than a tunnel. Use named identities, strong authentication appropriate to the access platform, specific destinations, approval, logging, and a way to end an active session. Keep control systems off direct public management paths.
A keyed VPN can provide an encrypted connection without, by itself, providing individual approval, multifactor authentication, or time-bounded authorization. Choose the complete access arrangement around those requirements. Test what the vendor cannot reach, as well as the maintenance task that must work.
Keep an operator-owned emergency procedure for the day the normal identity or internet service is unavailable. It should be controlled and testable, not a forgotten port-forward with a reassuring label.
Make the network explain the next fault
The operational view should answer a handful of useful questions: Did the site lose power? Did the link degrade before it failed? Is the application unavailable while the transport still works? What configuration changed?
A suitable monitoring platform can collect supported interface, radio, power, and service data. Configuration history is a separate requirement. A tool such as LibreNMS integrated with Oxidized can connect device monitoring with configuration revisions; it does not replace backups of HMI projects, controllers, historians, or other application state.
Protect those records as management infrastructure. Configuration exports may contain secrets. A sanitized copy useful for comparison is not necessarily a complete restore source. Have the responsible specialists demonstrate recovery for the systems they own.
Security inspection is another separate choice. If an IDS is appropriate, begin with an agreed observation plan and tune against known traffic. Do not turn an unfamiliar signature set into an inline process interruption. A sensor also cannot inspect traffic it never sees, or magically interpret the contents of every encrypted session.
Design the failure path the team can operate
Two links are not a recovery plan until their behavior is understood. Where Layer 2 is required, deliberately engineered spanning tree may be appropriate. Where the service permits routed boundaries, routing can give better fault containment. Neither choice is a universal upgrade ladder.
Trace shared power, structures, cable routes, and upstream dependencies. Agree on acceptable interruption with the utility and controls owner. Test link loss, degraded paths, restoration, and loss of management access. A fast protocol transition is useful only if the operational service recovers as intended.
The runbook should tell the person on call what to observe, whom to contact, and which actions are authorized. It should not require them to rediscover the network while the operator waits.
Cut over in stages, with an exit at each one
- Record the current flows, port assignments, configuration, and recovery access.
- Stage and test the new boundaries away from the running process where practical.
- Choose a migration order with the operators; lower-risk office or guest changes may be a useful first stage, but dependencies decide.
- Move one agreed group at a time. Verify its required functions and its denied paths.
- Stop or roll back at the pre-agreed trigger, not after optimism has consumed the maintenance window.
- Verify alarms, vendor-access closure, configuration capture, and the handoff with the people who will operate it.
What a successful handoff would demonstrate
The operator can identify the affected system without guessing. The controls specialist can confirm that required process communications still behave correctly. A vendor can do an approved job without receiving an invitation to the rest of the network. A second engineer can trace a flow and find the recovery procedure.
The acceptance record should demonstrate those outcomes. Counting the security features on a product page is a less demanding exercise, but it tells the operator considerably less.
If that is the kind of clarity your utility needs, see OT and SCADA network engineering or start a conversation about the operational problem. Do not send passwords, live control configurations, or sensitive site details through the inquiry form. A useful first conversation starts with the symptoms and constraints.